2019 Annual Inspections Complete

The annual inspections for all grade crossings were completed on 10/5/2019.

Kilkare Crossing Gets New Gates

The classic wooden gate arms that have protected Kilkare Rd. crossing for many years have been temporarily replaced with aluminum/fiberglass gates until new wooden gates can be fabricated. The original gates needed to be repainted and re-striped. After they were removed a close inspection revealed some wood damage. It was decided that fabricating new gates […]

Bond St. Crossing Back in Service on 10/23/2010

Bond St. Crossing is back in service.

Bond St. Crossing Out-Of-Service Starting 7/17/2010

Bond St. Crossing will be out-of-service starting 7/17/2010 and will remain out-of-service while the signal cabinet is being rebuilt. All train crews must flag the crossing during this time.

Bond St. Crossing Back In Service

Bond St. Crossing is back in service. Modifications to the mounting and alignment of the lights on the north and south signals have been completed.